December 2021 marks the end of the second year of a 3 year build program for the project. 2021 was a year of great progress with the site transforming as the waste bunker was completed 8m below the surface and the boiler structure reached 30m into the Rockingham skyline. We are proud to share this project update and thank all our project partners for their efforts during the year. The #accionateam on site have been awesome.

Please click on this link to see our latest drone fly over of the site: ERWTE December 2021 Drone Footage